Architect: Volkert & Associates (Mobile, Alabama)

Project Location: Mobile, Alabama

Four million dollars over budget at bid. A completion date that could not be changed. A time deadline of only seven months for construction. This was the project status when the City of Mobile asked White-Spunner Construction for help. White-Spunner Construction completed the project within budget while maintaining the original opening date. Immediately, the company spent time up front for value engineering and redesigning what might be considered the highest profile project in the history of Mobile. White-Spunner Construction entered into a contract with the City of Mobile in September. The goal to construct a 6,000 seat prestressed concrete baseball stadium was complete on April 17, the original opening date. Partnering with the original architect, the baseball team owner and the City of Mobile, the stadium was completed on time and within budget.